Construction update

What’s happening and what’s ahead?

Construction

  • Construction for new Library/MRC/Dean’s Suite wing continues.  Interior framing and infrastructure installations continue.  Scheduled for completion August 2017.
  • Construction of the new cafeteria continues.  Interior framing and infrastructure installations continue.  Scheduled for completion August 2017.
  • New Atrium and lecture hall building is enclosed.  Interior framing and infrastructure installations continue.  Block work to follow.
  • Temporary Gallery wall has been taken down.
  • Some temporary walls will be constructed in the Schurman tutorial corridors.
  • Glass curtain wall is being installed on new Library wing and courtyard side of new Atrium.

VRT

  • The new glass curtain wall assembly is complete.
  • Office relocations are complete.  Left to do – Punch list items and perimeter heat water hydronic balancing.
  • The design efforts for levels 6 and 7 floor renovations are currently underway.  Construction will tentatively begin in early Spring 2017. 

Community Practice Service Building

  • G. M. Crisalli & Associates is contractor.
  • Demolition of the existing Poultry Virus Lab and construction of the new building will begin spring 2017 with completion anticipated March 2018.

Check out the live construction cam feed here!